Aurelia Construction Updates

  • Conduit installation is 17% complete
  • Drop construction is ramping up with 58% of households committing to service have been installed.
    • If you haven’t signed up for service yet, there is still time. Please visit NuveraGigCities.com to get signed up while the construction crews are still in Aurelia. When they leave, your ability to transition to the fiber network will be delayed until crews can return.
  • Majority of construction requiring restoration and re-seeding is complete in the areas of East of Main St, Myrtle Street, Hill Street, Ridgeview Lane and Coombs Dr. Splicing will follow.
  • Construction will begin working to place mainline duct in street right-of-way (ROW) and alleys, starting west of Main Street and west 3rd Street.

Learn more about the construction process.