Fiber construction projects happen in five main steps. They are typically in the following order but sometimes order may vary slightly.
- Mainline construction. This is placing the main fiber line in either the public right-of-of ways or alleys.
- Cable pulling. Fiber is pulled through the main line that was placed.
- Mainline splicing and testing. Fiber optic splicing is the process of joining two separate fiber optic cables together. It is then tested for its strength.
- Drops to home. Facilities or “drops” are buried from the mainline to the customer’s home. This includes placing the fiber which will also be spliced and tested.
- Installation and customer connection. Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation their new fiber internet service.
Savage, MN 55378 Updates (East of Crest)
- Construction in Savage (East of Crest) start date has been moved to 2025 due to unforeseen circumstances.
- Before construction begins, flags and paint markings will be placed in the rights-of-way and/or alleyways where mainline construction will occur.
- Property owners in the current build area have or will receive construction communications prior to activity in their area and are encouraged to sign up for service as soon as possible.
- Residents are also able to check on status of the overall construction project in their community by visiting this page.
- Residents are encouraged to sign up early by calling Nuvera’s local team at 844.354.4111 or visiting NuveraGigCities.com.
- For business services, visit Nuvera.net/Business or talk to Nuvera’s local business team at 844.610.5300.