Hutchinson Construction Updates

  • Conduit installation is 13% complete
  • Drop construction is ramping up with 8% of households committing to service have been installed.
    • If you haven’t signed up for service yet, there is still time. Please visit NuveraGigCities.com to get signed up while the construction crews are still in Aurelia. When they leave, your ability to transition to the fiber network will be delayed until crews can return.
  • Majority of construction requiring restoration and re-seeding is complete in the areas of S Jefferson Rd, Airport Rd, and Edmonton Ave SE. Working on placing fiber in duct this week. Splicing will follow.
  • Construction will begin working to place mainline duct in street right-of-way (ROW) and alleys, starting west of Otter Lake and south of County Road 82.