Cokato Construction Updates
We’re committed to building the fastest, most reliable fiber network for our entire community.

Have a construction question or restoration request?

Fiber construction projects typically happen in the following order but may vary slightly.
- Site Preparation. Before construction begins, crews will mark utility lines in the area using paint and flags. Please do not remove flags or paint markings. Homeowners are responsible for marking any private underground systems, such as sprinkler lines or invisible fences.
- Mainline Construction. The main fiber line is placed in either the public right-of way or alley and then fiber pulled through.
- Drop Construction. Fiber is extended from the main line to individual homes. This step involves burying a line, or “drop”, and pulling fiber through to each address.
- Splicing. Fiber cables are joined together through a process called splicing and then tested to confirm the connection is strong and reliable. This step is done on both the mainline and the line going to each home.
- Installation. Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation of their new fiber internet service.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
Cokato, MN 55321 Updates
11/04/2025
C3, C4 & C6
The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
C1 & C5
The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/28/2025
C6 & C4
The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Splicing is in complete. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Drops to customer homes are complete. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
C1
The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/21/2025
C6 & C3
The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Splicing is complete. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Cable pulling is complete. Drops to customer homes are in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Drops to customer homes are complete. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/14/2025
C6
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C3 & C4
Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Cable pulling and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Cable pulling is complete and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
10/07/2025
C6
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Cable pulling is complete and splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Cable pulling and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Cable pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/30/2025
C6
Splicing is completed. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Splicing will start this week. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1, C4 & C5
Cable pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/25/2025
C6
Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Cable pulling and drops to customer homes are complete. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Cable pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Cabling pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/16/2025
C6
Cable pulling and drops to customer homes are complete. Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Cable pulling and drops to customer homes are complete. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Cable pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Mainline construction is complete. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/08/2025
C6
Mainline construction is complete. The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
C3 & C1
Mainline construction is complete. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Mainline construction is complete and cable pulling is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/02/2025
C6
Cable pulling and drops to customer homes are complete. Mainline construction is in progress. The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Cable pulling and drops to customer homes are complete. Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Drops to customer homes are complete. Mainline construction and cable pulling are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C1
Drops to customer homes are complete. Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
08/26/2025
C6
Mainline construction, cable pulling and drops to customer homes are in progress.
The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Mainline construction, cable pulling and drops to customer homes are in progress.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C4 & C1
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction will begin the week of August 25 and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
08/19/2025
C6, C3, C4 & C1
Mainline construction, cable pulling and drops to customer homes are in progress.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
08/12/2025
C6, C3 & C4
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C5 & C1
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
08/05/2025
C6, C3 & C4
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C5 & C1
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
07/29/2025
C1
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C3
Mainline construction is in progress.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C4
Mainline construction will begin the week of July 29 and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C5
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
C6
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is August 2025 but may vary due to circumstances out of Nuvera’s control.
07/22/2025
C3
Mainline construction is in progress and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
C6
Mainline construction is in progress and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Drops to customer homes are also in progress.
07/15/2025
C6
Mainline construction is in progress and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Drops to customer homes are also in progress.
05/20/2025
- The project is projected to be completed over a 2-year period. Some neighborhoods began construction in 2024 and the remainder will begin in 2025.
- Before construction begins, flags and paint markings will be placed in the rights-of-way and/or alleyways where mainline construction will occur.
- Property owners in the current build area have or will receive construction communications prior to activity in their area and are encouraged to sign up for service as soon as possible.
- Residents are also able to check on status of the overall construction project in their community by visiting this page.
- Residents are encouraged to sign up early by calling Nuvera’s local team at 844.354.4111 or visiting NuveraGigCities.com.
- For business services, visit Nuvera.net/Business or talk to Nuvera’s local business team at 844.610.5300.
Not a Nuvera Customer?
Sign up for presale service to get fiber facilities buried to your home during construction.