Prior Lake Sand Point Construction Updates
We’re committed to building the fastest, most reliable fiber network for our entire community.

Have a construction question or restoration request?
Fiber construction projects happen in five main steps. They are typically in the following order but sometimes order may vary slightly.
- Mainline construction. This is placing the main fiber line in either the public right-of-of ways or alleys.
- Cable pulling. Fiber is pulled through the main line that was placed.
- Mainline splicing and testing. Fiber optic splicing is the process of joining two separate fiber optic cables together. It is then tested for its strength.
- Drops to home. Facilities or “drops” are buried from the mainline to the customer’s home. This includes placing the fiber which will also be spliced and tested.
- Installation and customer connection. Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation their new fiber internet service.
Prior Lake, MN 55373 Updates
02/04/2025
SP3
Due to winter weather, fiber construction is temporarily paused. Work will resume in the spring. The estimated date for this area to be fiber-ready is 2025, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP6
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP5
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP2
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP4
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
01/07/2025
SP3
Field staking is scheduled to begin next week.
SP6
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP5
Splice testing is being reviewed.
The estimated date for this area to be fiber-ready is January, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP4
Splice testing is being reviewed.
The estimated date for this area to be fiber-ready is January, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
12/31/2024
SP6
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP5
The estimated date for this area to be fiber-ready is January, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP4
The estimated date for this area to be fiber-ready is January, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
12/17/2024
SP6
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP5
Splice testing is being reviewed.
SP2
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP4
Splice testing is being reviewed.
The estimated completion date for this area is late December but may vary. Check back here for updates.
12/10/2024
SP6
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP5
Splice testing is being reviewed.
SP2
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
SP4
Splice testing is in progress.
The estimated completion date for this area is late December but may vary. Check back here for updates.
12/04/2024
SP6
Splice testing is being reviewed.
SP5
Splice testing is being reviewed.
SP2
Splice testing is being reviewed.
SP4
Splice testing is in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
11/26/2024
SP6
Splicing is in progress.
SP5
Splice testing is in progress.
SP2
Splice testing is complete.
SP4
Splicing is in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
11/19/2024
SP6
Splicing, cable placing and drops in progress.
SP5
Splice testing is in progress.
SP2
Testing is in almost complete.
SP4
Splicing and cable pulling are in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
11/12/2024
SP6
Drops are in progress.
SP5
Splicing is in progress.
SP2
Testing is in almost complete.
SP4
Drops and cable pulling are in progress. The estimated completion date for this area is late November but may vary. Check back here for updates
11/05/2024
SP6
Drops and cable pulling are in progress.
SP5
Splicing is in progress.
SP2
Testing is in progress.
SP4
Drops and cable pulling are in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
10/29/2024
SP6
Mainline construction is in progress.
SP5
Splicing is in progress.
SP2
Testing is in progress.
SP4
Cleanup is in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
10/22/2024
SP6
Mainline construction is in progress.
SP5
Splicing is in progress.
SP2
Splicing is in progress.
SP4
Cable pulling and drops are in progress.
The estimated completion date for this area is late November but may vary. Check back here for updates.
10/15/2024
SP6
Mainline construction is in progress.
SP5
Splicing is in progress.
SP2
Splicing is in progress.
SP4
Cable pulling and drops are in progress.
10/08/2024
SP6
Mainline construction will start soon.
SP5
Splicing is in progress.
SP2
Splicing is in progress.
SP4
Cable pulling and drops are in progress.
10/01/2024
SP6
Mainline construction will start soon.
SP5
Drops to customer homes are in progress.
SP2
Splicing is in progress.
SP4
Mainline construction is almost complete and cable pulling will start this week.
09/24/2024
242 drops are now completed overall.
SP7
Splicing is completed.
SP6
Mainline construction will start soon.
SP5
Drops to customer homes will be finished soon.
SP2
Splicing has begun.
SP4
Close to finishing mainline construction (near the intersection of Birchwood and Shady Beach). Cable pulling will start next week.
09/17/2024
242 drops are now completed overall.
SP7
Splicing is complete and is being tested.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP5
Drops to customer homes will be finished soon.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Splicing will begin soon.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP4
Close to finishing mainline construction (near the intersection of Birchwood and Shady Beach). Cable pulling will start next week.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
09/10/2024
231 drops are now completed overall.
SP7
Splicing is complete and is being tested.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP5
Drops to customer homes are in progress.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Splicing will begin soon.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP4
Drops are in progress
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
09/03/2024
SP7
Splicing is complete and is being tested. The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP5
Drops to customer homes are in progress.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Splicing will begin soon.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP4
Mainline construction and cable pulling is in progress.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
08/27/2024
SP7
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP5
Drops to customer homes are in progress.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP2
Drops to customer homes are in progress and splicing will begin soon.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
SP4
Mainline construction and cable pulling is in progress.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
08/20/2024
SP7
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP5
Drops to customer homes are in progress and well as cable pulling.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP2
Splicing and testing fiber will begin soon. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction is in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
08/13/2024
SP7
Drop splicing/testing is complete.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP5
Drops to customer homes are in progress, along with cleanup. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
SP2
Drops to customer homes are complete. Splicing and testing fiber will begin soon. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction is in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP6
The estimated completion date for this area is October but may vary due to circumstances out of Nuvera’s control.
SP3
This area is scheduled for 2025.
08/06/2024
SP7
Drop splicing/testing is in progress. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP5
Drops to customer homes are in progress. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
SP2
Drops to customer homes are complete. Splicing and testing fiber will begin soon. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction is in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP6
The estimated completion date for this area is October but may vary due to circumstances out of Nuvera’s control.
SP3
This area is scheduled for 2025.
07/30/2024
SP7
Mainline and drop splicing/testing is in progress. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP5
Cable pulling is nearly complete.
SP2
Mainline fiber pulling is near completion and drops to customer homes are in progress. Splicing and testing fiber will begin soon. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction is in progress on the west end of the project and cable is being pulled.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP6
The estimated completion date for this area is October but may vary due to circumstances out of Nuvera’s control.
SP3
This area is scheduled for 2025.
7/23/2024
SP7
Mainline and drop splicing/testing is in progress. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP5
Drops to customer homes and cable pulling are in progress.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
SP2
Mainline fiber pulling is near completion and drops to customer homes are in progress. Splicing and testing fiber will begin soon. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction is in progress and cable is being pulled.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
SP6
The estimated completion date for this area is October but may vary due to circumstances out of Nuvera’s control.
SP3
This area is scheduled for 2025.
7/16/2024
SP7
Yard restoration and cable pulling are in progress.
Splicing and testing fiber will begin this week. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
SP5
Drops to customer homes and cable pulling is in progress.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
SP2
Yard restoration and cable pulling are in progress.
Drops to customer homes will begin this week. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
The estimated completion date for this area is September, but may vary due to circumstances out of Nuvera’s control.
SP4
Mainline construction began in mid-June and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring to place conduit for fiber-optic line to be pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
The estimated completion date for this area is September, but may vary due to circumstances out of Nuvera’s control.
SP6
The estimated completion date for this area is October, but may vary due to circumstances out of Nuvera’s control.
SP3
This area is scheduled for 2025.
Not a Nuvera Customer?
Sign up for presale service to get fiber facilities buried to your home during construction.