Dufferin Construction Updates

Nuvera Fiber Internet Expansion

Select an option for yard restoration. Thank you!

Fiber construction projects happen in five main steps.  They are typically in the following order but sometimes order may vary slightly.

  1. Mainline construction.  This is placing the main fiber line in either the public right-of-of ways or alleys.
  2. Cable pulling.  Fiber is pulled through the main line that was placed.
  3. Mainline splicing and testing.  Fiber optic splicing is the process of joining two separate fiber optic cables together. It is then tested for its strength.
  4. Drops to home.  Facilities or “drops” are buried from the mainline to the customer’s home.  This includes placing the fiber which will also be spliced and tested.
  5. Installation and customer connection.  Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation their new fiber internet service.

Savage, MN 55378 Updates (Dufferin)

12/31/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

12/17/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

12/10/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

12/03/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

11/26/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

11/19/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

11/12/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

11/05/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

10/29/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

10/22/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

10/15/2024

Great news!  This area is ready for fiber!  In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.

10/08/2024

Splicing is complete. 

10/01/2024

Splicing is occurring in Dufferin D1.

09/24/2024

Continuing to finish up drops. 

09/17/2024

Finishing up drops. 

09/10/2024

Splicing is complete in D6 and D7. 

Cleanup is occurring in D1.  

09/03/2024

Splicing is complete in D6 and in progress in D7. 

08/27/2024

Splicing is complete in D1 and D2. Splicing is in progress in D6 and D7.

08/20/2024

Splicing is in progress.

The estimated completion date for this area is August – September but may vary due to circumstances out of Nuvera’s control.

08/13/2024

Splicing is complete in SA1 and almost complete in SA2. Splicing has started in SA6. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.

The estimated completion dates for this area is August but may vary due to circumstances out of Nuvera’s control.  

07/23/2024

All drops to customer homes are completed and restoration of lawns is in progress.  

Splicing and testing fiber is in progress in some areas.  You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.

The estimated completion dates for this area is August but may vary due to circumstances out of Nuvera’s control.  

7/16/2024

Drops to customer homes are in progress.  Current and new customers are contacted by mailers or door tags directly at your home before we start digging.   The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.

Splicing and testing fiber are also in progress.  You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is GIG-fast.

The estimated completion dates for this area is July-September, but may vary due to circumstances out of Nuvera’s control.  