Hutchinson Construction Updates
We’re committed to building the fastest, most reliable fiber network for our entire community.

Have a construction question or restoration request?

Fiber construction projects typically happen in the following order but may vary slightly.
- Site Preparation. Before construction begins, crews will mark utility lines in the area using paint and flags. Please do not remove flags or paint markings. Homeowners are responsible for marking any private underground systems, such as sprinkler lines or invisible fences.
- Mainline Construction. The main fiber line is placed in either the public right-of way or alley and then fiber pulled through.
- Drop Construction. Fiber is extended from the main line to individual homes. This step involves burying a line, or “drop”, and pulling fiber through to each address.
- Splicing. Fiber cables are joined together through a process called splicing and then tested to confirm the connection is strong and reliable. This step is done on both the mainline and the line going to each home.
- Installation. Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation of their new fiber internet service.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
Hutchinson, MN 55350 Updates
11/04/2025
164/171/173/174/175
The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
166/170
Splicing is in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
172
Cable pulling is complete. Drops to customer homes and splicing are in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
178
Drops to customer homes and cable pulling are complete. Splicing has not started. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/28/2025
164/171/173/174/175
Splicing is in progress. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
170
Splicing has not started yet. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
166
Cable pulling is complete. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
172
Cable pulling and drops to customer homes are in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
178
Drops to customer homes and cable pulling are in progress.
The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/21/2025
164/171/173/174/175
Splicing is in progress. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
170
Splicing has not started yet. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
166
Drops to customer homes are complete and cable pulling is in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
172
Cable pulling and drops to customer homes are in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
178
Mainline construction is complete and drops to customer homes are in progress. The estimated completion date for this area is December 2025 but may vary due to circumstances out of Nuvera’s control.
10/14/2025
164/171/174/175
Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
173/170
Mainline construction, cable pulling and drops to customer homes are complete. Splicing has not started yet. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
166
Drops to customer homes are in progress. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
172
Cable pulling and drops to customer homes are in progress. The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
10/07/2025
164
Drops to customer homes are complete and splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
174/175/171
Splicing is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
173
Drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
170
Mainline construction and drops to customer homes are complete. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
166/172
Construction has started and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
The estimated completion date for this area is November 2025 but may vary due to circumstances out of Nuvera’s control.
09/30/2025
164/171/174/175
Mainline construction and cable pulling are complete. Drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
173
Mainline construction is complete and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
170
Mainline construction is in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/25/2025
164/171/174/175/173
Mainline construction and cable pulling are complete. Drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
170
Construction has started and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/16/2025
164/171/174/175
Mainline construction and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
173
Construction has started and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/09/2025
164/171
Mainline construction and drops to customer homes are in progress. The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
174/175
Mainline construction and drops to customer homes are in progress. The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
09/02/2025
164
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
171
Mainline construction and drops to customer homes are in progress.
The estimated completion date for this area is September 2025 but may vary due to circumstances out of Nuvera’s control.
174/175
Mainline construction is in progress and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
The estimated completion date for this area is October 2025 but may vary due to circumstances out of Nuvera’s control.
08/19/2025
R164
Mainline construction and drops to customer homes are in progress. Check back for progress updates on your neighborhood.
08/11/2025
R164
Mainline construction is in progress. Check back for progress updates on your neighborhood.
08/05/2025
R164
Mainline construction is in progress. Check back for progress updates on your neighborhood.
07/29/2025
RT164, RT166, RT170, RT171, RT172, RT173, RT174/175, RT178
Mainline construction will begin soon and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring will take place in either the public right-of way or alley and then fiber pulled through.
Check back for progress updates on your neighborhood.
Not a Nuvera Customer?
Sign up for presale service to get fiber facilities buried to your home during construction.