Olivia Construction Updates
We’re committed to building the fastest, most reliable fiber network for our entire community.

Have a construction question or restoration request?

Fiber construction projects happen in five main steps. They are typically in the following order but sometimes order may vary slightly.
- Mainline construction. This is placing the main fiber line in either the public right-of-of ways or alleys.
- Cable pulling. Fiber is pulled through the main line that was placed.
- Mainline splicing and testing. Fiber optic splicing is the process of joining two separate fiber optic cables together. It is then tested for its strength.
- Drops to home. Facilities or “drops” are buried from the mainline to the customer’s home. This includes placing the fiber which will also be spliced and tested.
- Installation and customer connection. Once a neighborhood is fiber-ready, current customers and new customers that signed up for service will be contacted about the installation their new fiber internet service.
Olivia, MN 56277 Updates
01/07/2025
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
12/31/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
12/17/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
12/10/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
12/03/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
11/26/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
11/19/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
11/12/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
11/05/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
10/29/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
10/22/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
10/15/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
10/08/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
10/01/2024
01
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
02
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
03
Great news! This area is ready for fiber! In the upcoming weeks, new customers that signed up for fiber will be contacted for installation and current customers will be contacted to migrate to fiber.
09/24/2024
01
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
02
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
03
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
09/17/2024
01
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
02
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
03
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
09/10/2024
01
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
02
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
03
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
09/03/2024
01
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
02
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
03
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
08/27/2024
01
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
02
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
03
Splicing and testing is in progress and should be completed this week.
The estimated date for this area to be fiber-ready is September, after which fiber installations will be on-going. Completion dates may vary. Watch here for more details.
08/20/2024
01
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
02
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
03
Splicing and testing fiber is in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
08/13/2024
01
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
02
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
03
Splicing and testing fiber should begin the week of August 19. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is Gig-fast.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
08/06/2024
01
Splicing is complete.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
02
Splicing is complete.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
03
Cable has been pulled through the mainline.
Drop construction to customer homes is complete and splicing/testing the fiber in this drops is starting.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
07/30/2024
01
Splicing and testing fiber is in progress.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
02
Splicing and testing fiber is in progress.
The estimated completion date for this area is August but may vary due to circumstances out of Nuvera’s control.
03
Drops to customer homes are in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
07/23/2024
01
Splicing and testing fiber is in progress.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
02
Splicing and testing fiber is in progress.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
03
Mainline construction is complete and drops to customer homes are in progress.
The estimated completion date for this area is September but may vary due to circumstances out of Nuvera’s control.
07/16/2024
01
-Drops are in progress.
Splicing and testing fiber is in progress. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is Gig-fast.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
02
Mainline construction is complete and cable is being pulled. Splicing/testing and drops to customer homes are in progress.
The estimated completion date for this area is August, but may vary due to circumstances out of Nuvera’s control.
03
Mainline construction started the week of July 9 and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring to place conduit for fiber-optic line to be pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
Drops to customer homes are also in progress. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
The estimated completion date for this area is September, but may vary due to circumstances out of Nuvera’s control.
07/01/2024
01
Drops to customer homes continues.
02
Drops to customer homes continues.
06/24/2024
02
Splicing and testing fiber will start the week of July 1. You may see a Nuvera splicing trailer in your neighborhood. Our team will fuse the individual fibers that will eventually connect to your home or business. Then we test the speed of light as it passes through the fiber to make sure your connection is Gig-fast.
06/17/2024
01
Mainline construction is complete. Drops to customer homes are in progress. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
02
Drops to customer homes are in progress. Current and new customers are contacted by mailers or door tags directly at your home before we start digging. The Nuvera team places the fiber optic cable from the pedestal up to the Network Interface Device, or NID, attached to the outside of your home. The crew then installs what’s known as a Fiber Optic Network Terminal, or O N T, inside your home. This is the heart of your new fiber internet connection, linking directly to the fiber in the NID outside.
06/10/2024
01
Mainline construction is complete.
02
Mainline and drop construction continues.
5/31/2024
01
Construction began the week of May 20, 2024, and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring to place conduit for fiber-optic line to be pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
Check back for progress updates on your neighborhood.
02
Construction began the week of May 27, 2024, and includes several important steps. The first steps you will see in your neighborhood are:
Marking of utilities with paint and flags in the construction area. Please do not remove flags or paint markings. Flags will be removed after construction is complete and the paint markings will fade on their own.
Once locate flags are placed in your yard you must locate and mark any private underground facilities such as: invisible fencing, irrigation lines, private power, etc.
Main line boring to place conduit for fiber-optic line to be pulled through.
Construction may cause minor disruption to your yard or landscaping. Crews will restore any impacted areas following construction.
Check back for progress updates on your neighborhood.
5/15/2024 Updates
- Construction in Olivia will begin in late May.
- The project will be completed over a 2-year period, with some neighborhoods beginning construction in 2024 with the remainder in 2025.
- Before construction begins, flags and paint markings will be placed in the rights-of-way and/or alleyways where mainline construction will occur.
- Property owners in the current build area have or will receive construction communications prior to activity in their area and are encouraged to sign up for service as soon as possible.
- Residents are also able to check on status of the overall construction project in their community by visiting this page.
- Residents are encouraged to sign up early by calling Nuvera’s local team at 844.354.4111 or visiting NuveraGigCities.com.
- For business services, visit Nuvera.net/Business or talk to Nuvera’s local business team at 844.610.5300.
Not a Nuvera Customer?
Sign up for presale service to get fiber facilities buried to your home during construction.